Hydraulic Catwalks on Drilling Rigs and the Pipe Handoff

A hydraulic catwalk moves a tubular between the pipe rack and the drill floor. On a common design, a joint enters a trough and a powered carriage presents one end near the V-door for pickup. The receiving equipment then takes the load. A catwalk may lift the heaviest joint on the list yet still be unsuitable because the joint is too long, its accessories catch on the carrier or its end lands outside the pickup envelope.

Trace the joint from rack to elevators

Sketch the rack, loading deck, trough, V-door and intended pickup point in side view. Mark where the joint can roll sideways, where its end travels lengthwise and where the receiving equipment begins to lift. The box can be well inside the drill floor while the other end still rests in the trough. During that interval the two systems share control of the same joint.

Look at the reverse movement separately. A joint laid down after a trip may carry a thread protector or have a larger diameter at one end. Ask how the receiving deck contains it after delivery and where the following joint will wait. A clear route up the V-door does not establish a clear discharge path back to the pipe rack. Keep people outside roll, travel and pinch zones during tests and transfers.

From pipe rack to drill-floor handoff. The catwalk transports and presents a tubular. The lifting equipment on the floor must receive it within its own working envelope.
The catwalk transports and presents a tubular. The lifting equipment on the floor must receive it within its own working envelope.

Catwalk components and what each one does

On the Canrig PC3000-26, follow three separate movements in sequence. The joint rolls across the deck, the carrier rises and the skate moves the pipe lengthwise. The PC3000-26 User’s Manual, chapter 3 identifies the parts used for each movement.

ComponentFunction on the PC3000-26
Pipe-rack arms and hydraulic legsSupport the tubulars beside the deck. The leg position sets the slope toward or away from the catwalk.
IndexersTilt to feed pipe laterally toward the carrier or return it toward the rack.
Safety pinsRise at the sides of the carrier to keep the tubular from rolling across or out of it.
Carrier trough, ramp and rollersThe trough cradles the joint. The ramp and rollers guide the carrier along its inclined travel.
Carrier winch and lift cablesRaise and lower the loaded carrier. Both lift cables are needed for normal operation.
Skate and its driveThe skate travels lengthwise inside the trough to present the pipe end to the floor or support it on laydown.
KickersDischarge the tubular sideways from the lowered carrier toward the selected rack.
Hydraulic power unit and control systemThe power unit supplies hydraulic flow. Commands from the console or radio pass through the controller, which inhibits incompatible movements such as indexing with the carrier raised.

For the Model 3000, Canrig lists a maximum tubular weight of 10,000 lb, length of 45 ft, outside diameter of 20 in and floor heights of 18–35 ft. Its listed 20–54 seconds describes one handling cycle. The machine’s approved operating duty comes from the installed configuration and its manual. Canrig Automated Power Catwalk specifications.

Check weight, length, diameter and floor height

The equipment sheet should give the acceptable tubular weight, length and diameter as well as the supported rig-floor-height envelope. Check the joint as delivered, including attached equipment where the manufacturer permits such a configuration. Diameter determines whether the trough and handling features can contain the item. Actual length governs overhang and pickup geometry. The rig-floor height and horizontal delivery point determine whether the receiving device can engage without pulling the joint sideways.

Record the rig and catwalk reference elevations. A civil layout may give drill-floor height above well-center ground level while the catwalk stands on a separate pad. A height difference between the pads changes the actual rise the machine has to bridge. Capture the measured value and the model-specific dimension definition, especially after a rig move or civil works.

The delivery truck’s dimensions can also mislead the layout review. Expro gives a packed length of 43 ft for this model and a machine length of 76–93.8 ft in the specifications. Plot the machine in its working position before marking vehicle access, pipe racks and the receiving point. The transport footprint understates the space the rig must provide.

The handoff continues to drill pipe elevators and other pipe-handling equipment. Checking the receiving device clarifies whether a delivery position is actually compatible.

Measure rise from the catwalk’s own reference. A floor elevation taken at well center may differ from the vertical rise above the machine pad. Use the manufacturer’s reference points.
A floor elevation taken at well center may differ from the vertical rise above the machine pad. Use the manufacturer’s reference points.

Example of a load that passes one check and fails another

Expro’s March 2025 hydraulic catwalk sheet lists pipe limits of 8,800 lb, 50 ft in length and 30 inches in OD, with a rig-floor height range of 10–42 ft. Suppose the proposed single weighs 7,150 lb and measures 51 ft overall, and the floor stands 36 ft above the machine’s stipulated reference. The listed weight margin is 1,650 lb and the floor height falls within range. The joint exceeds the published length by one foot.

Do not trade surplus lifting capacity for overlength. The figures describe different limitations. A shift note reading “within catwalk capacity” would lose the detail that disqualifies this item. Record the controlling length and obtain a qualified alternative or a documented engineering disposition for the exact equipment and geometry.

Check weight, length and floor height separately. Hypothetical joint against the Expro March 2025 sheet: 7,150 lb and a 36-ft floor fit the cited ranges; 51 ft exceeds the 50-ft length.
Hypothetical joint against the Expro March 2025 sheet: 7,150 lb and a 36-ft floor fit the cited ranges; 51 ft exceeds the 50-ft length.
Pipe deck, catwalk and V-door on the Transocean Searcher
The deck view follows the transfer route from pipe storage to the V-door. Photo by O-P Holmvassdal (CC BY-SA 3.0).

What to demonstrate before production transfer

A useful commissioning record identifies the pickup and discharge positions, method of retaining the pipe, control stations, communications and the boundary between catwalk operator and driller. Confirm protective devices and responses through the approved commissioning procedure. A cycle-time measurement means little if people have to enter the machine envelope to complete a normal handoff. Record an exception against its specific movement so the receiving crew knows what remains unresolved.

Check center of gravity at the changes of support

As a static illustration only, assume a 6,000-lbf assembly rests on two level supports 12 ft apart, with its center of gravity 8 ft from support A and 4 ft from support B. Taking moments about A gives a B reaction of 6,000 × 8 ÷ 12 = 4,000 lbf; A carries the other 2,000 lbf. A central load would give 3,000 lbf on each. The same total weight can therefore produce different local reactions.

A real catwalk moves and inclines, and its support points change as the tubular approaches handoff. Use the actual assembly’s center of gravity, accessory retention and the manufacturer’s permitted load distribution. This beam example is not a method for deriving a catwalk rating or accepting an unsupported overhang.

Working hours and preventive maintenance on the Canrig PC3000

Keep separate records for carrier-winch running hours, catwalk operating days and lift-cable ton-miles. A 12-hour tour with two hours of winch operation adds two winch hours. These counters govern different maintenance decisions. The Expro load envelope above belongs to a different machine.

When or what triggers the workPreventive maintenance to record
Daily, PC3000-26Clean and inspect the ramp, roller guides, pivot pockets, skate groove, indexers, kickers and stop pins. For hands-on work, follow the isolation procedure. Access beneath an elevated carrier requires the designated mechanical stop bar.
Weekly, PC3000-26Grease the lift-arm shaft, kicker-cylinder and pivot fittings, safety-pin cylinders and other points on the lubrication chart. Record blocked fittings and damage discovered during greasing.
Winch operating hours and load historyFor carrier winch M10529 on a PC3000 or PC4000, use the three-month average of hours per month. Where the severe-load criterion is absent, 30 h/month calls for a gear-oil change every 12 months and 100 h/month calls for one every six months. Over 200 h/month, or more than 75% of lifts above 75% of rated load, shortens it to three months.
Cable condition or ton-mile limitReplace a kinked, frayed or otherwise damaged lift cable. Also track the manufacturer’s ton-mile retirement limit for the installed cables. If one lift cable fails, suspend pipe transfer and follow Canrig’s recovery instructions.
1,000 operating days or five years, whichever comes firstFor the PC3000, schedule the major inspection. The bulletin specifies visual checks and magnetic-particle examination at identified locations, including ramp pivot posts and winch mounts. Record the running hours and inspection results separately.

For the PC3000-26 cleaning and greasing schedule, see chapter 6 of the user’s manual. Canrig specifies the oil-use categories in PC-044, table 1, lift-cable retirement in Catwalk Bulletin 26, and structural inspection in PC-052, revision 2. Check the installed serial number, winch part number and applicable bulletin revisions before entering the intervals in the rig maintenance system.

Field comparison

CheckUse this evidenceFrequent blind spot
LoadMaximum actual single, including permitted accessoriesA list based on average pipe weight
GeometryOverall length, OD profile and measured rig-floor heightLong pony assemblies or protruding accessories
HandoffPickup position relative to elevators or handlerTreating the V-door edge as the pickup point
LaydownRack containment and return clearanceConfirming only the pickup direction
Drill pipe stacked outdoors in North Dakota
The pipe racks are the starting point for a transfer to the rig floor. Photo by Joshua Doubek (CC BY-SA 3.0).

What to record in the field

Check or recordJob-specific entry
Record the catwalk model, configuration and source of its limits.
Compare measured tubular extremes with the load, length and diameter envelope.
Mark the support and handoff position in both directions.
Identify conflicting movements, the control owner and unresolved restrictions.
Additional technical figures (5)
Handoff requires both delivery and reception. The catwalk can complete its travel even when the receiving equipment cannot engage the tubular at the delivered position.
The catwalk can complete its travel even when the receiving equipment cannot engage the tubular at the delivered position.
Follow support through the transfer. The point of support changes along the path. Identify communication and control ownership at the handoff.
The point of support changes along the path. Identify communication and control ownership at the handoff.
The return movement has its own constraints. Use a separate check for the laydown direction. A successful pickup does not establish safe or unobstructed return.
Use a separate check for the laydown direction. A successful pickup does not establish safe or unobstructed return.
Surplus lifting capacity cannot offset excessive length. Each percentage is relative to its own published maximum. A 51-ft load uses 102% of the illustrative model’s 50-ft length limit.
Each percentage is relative to its own published maximum. A 51-ft load uses 102% of the illustrative model’s 50-ft length limit.
Three drawings to reconcile before the move. The machine sheet, pad references and actual tubular geometry must describe the same transfer.
The machine sheet, pad references and actual tubular geometry must describe the same transfer.

Questions from the field

Is the catwalk the same as the V-door ramp?

The ramp provides the inclined route. A powered catwalk includes equipment that controls transport and presentation of the tubular.

Can a short pup joint use the same arrangement as drillpipe?

Check the minimum supported length, retention and the approved carrier or basket. A small item may not engage the normal handling features.

Does a hydraulic catwalk replace elevators?

The catwalk presents the tubular. The designated receiving equipment takes control for hoisting in the applicable rig configuration.

Crew handling pipe on the derrick floor before a trip
The rig floor is the receiving end of the tubular transfer route. Photo by Joshua Doubek (CC BY-SA 3.0).

Technical references

IADC Drilling Manual (2015), Rotating & Pipehandling Equipment. Pages RP-2–RP-3, Pipehandling and powered catwalks.

Eni Corporate University, Drilling Rigs. Pages 312–313, pipe rack and pick-up/laydown machine.

Expro, Frank’s TRS Hydraulic Catwalk. Specifications, March 2025, revision 2.0.