Subsea Wellhead Anatomy: Follow the Casing Load and Annulus Seal

A subsea wellhead supports casing strings at the seabed, seals the annuli between them and provides the connection for the blowout preventer (BOP) or production tree. On a cross-section, follow the suspended weight down to a shoulder. Then follow the possible pressure path up the outside of the same hanger. The two paths explain why landing a string and sealing its annulus are separate milestones.

Read the wellhead from the seabed upward

The conductor and its low-pressure housing establish the foundation. The high-pressure housing lands within this assembly and supplies the internal profiles on which subsequent equipment relies. The external profile near its top accepts the matching connector. In the conventional arrangement illustrated in the SPE handbook, successive mandrel hangers stack above a primary landing shoulder. Other designs change how particular hangers are supported; the section drawing for the installed model settles the question.

A casing hanger carries the string hanging below it. Its outside diameter and the inside of the housing form the location for an annular seal assembly, often called a packoff. Flow-by passages allow displaced fluid and cement returns to pass the hanger during installation. A drawing showing these passages is consistent with a hanger that has landed while the annulus still communicates. The installation state determines which seals can be credited.

Read the nested housings. The housing supports the hanger while the packoff closes the annular path. Sketch shows one hanger in section.
The housing supports the hanger while the packoff closes the annular path. Sketch shows one hanger in section.

Three boundaries on one cross-section

Start with the load boundary. Mark the casing-to-hanger connection, the hanger shoulder and the receiving shoulder beneath it. Next mark the annular pressure boundary across the hanger seal. Finally mark the separate pressure boundary at the upper connector gasket. A test on one of these boundaries only helps diagnose another if the test configuration actually exposes it to the specified differential.

A wear bushing shields landing and sealing surfaces from passing tools. A lockdown bushing serves a different load path. During production, thermal expansion of the casing can push upward on the hanger and its annulus seal. Trace the retaining load into the housing and compare it with the installed lockdown capacity. The seal can have an integral lock, and some designs use a separate bushing. The cross-section and load case establish which component carries the uplift. API Specification 17D, §8.8.1 (2011 edition) illustrates these functions.

The mudline suspension guide describes a different way to carry casing loads offshore. The marine drilling riser guide identifies the equipment above a subsea drilling stack.

Where casing weight goes. In the conventional stacked-hanger arrangement, the conductor system ultimately transfers load into the foundation.
In the conventional stacked-hanger arrangement, the conductor system ultimately transfers load into the foundation.

Worked handover: the hanger landed and the seal test is outstanding

Suppose a casing crew records that a mandrel hanger landed at the expected elevation. The cement return record is complete. The shift report says “casing hung” and the next crew asks if the annulus can be marked isolated. The first two records support a mechanical and a cementing event. Neither specifies the packoff part, set indication or pressure-test boundary.

On the test sketch, identify the space that will be pressurized, the proposed seal, the pressure on its opposite side and any tool seals that could mask the intended path. Record the approved acceptance basis beside the actual result. If the test chart is outstanding, the handover can state precisely what has been demonstrated and which evidence is still due. No generic pressure value can close that gap.

Two evidence trails on the same hanger. Landing and sealing are separate events with separate evidence.
Landing and sealing are separate events with separate evidence.
Marine drilling riser joints with buoyancy modules stacked in a yard
Marine drilling riser joints form part of the temporary connection above subsea well equipment. Photo by Andyminicooper (CC BY-SA 3.0).

Quantify a pressure-induced load without assigning it to the wrong component

A verified pressure boundary with an effective projected area of 25 in² under a 4,000-psi differential has a 100,000-lbf pressure-area term. The direction follows the pressure boundary shown on the cross-section. The 25 in² is a hypothetical effective area taken from a drawing, not the housing bore, the gasket contact area or a generic connector dimension.

Mark the two pressure regions, the effective seal diameter or area and the surfaces that carry the resulting reaction. The load may add to or oppose another axial load depending on geometry and well state. Separately identify casing suspension, riser-induced bending and cyclic loads. A pressure test of one seal and an observed landing load are different entries in that integrity record.

When comparing a vendor’s wellhead system with the well design, start with the high-pressure housing bore and profile, the number and size of casing hangers it accepts, and the qualified pressure and combined loading for the proposed stack. Then identify which parts a later intervention would have to access. A larger nominal pressure rating alone says little about bending fatigue or the retrievability of an installed annulus seal.

Field comparison

PartWhat the part providesUseful handover evidence
Conductor housingFoundation and location for the high-pressure housingAs-installed configuration and landing survey
High-pressure housingInternal support and seal profiles, external connector profileModel, profile and bore-protection status
Mandrel hangerCasing suspension and flow-by during installationHanger identity and as-landed record
Annulus sealIsolation between hanger and housing at the intended boundarySetting record and applicable test trace
Engineers standing on a subsea blowout preventer before shipment
This is the drilling BOP before deployment to its subsea connection. Photo by Matthew Colvin de Valle (CC BY 2.0).

What to record in the field

Check or recordJob-specific entry
Record conductor and high-pressure housing model numbers and the as-built casing sizes.
Sketch the load path of the current string and identify the receiving shoulder.
Mark which packoffs have test evidence and which operations changed the configuration afterward.
Record connector profile, installed protective devices and the next expected running tool.
Additional technical figures (5)
Trace a potential annular leak. A test only challenges the intended interface when the high- and low-pressure regions are correctly identified.
A test only challenges the intended interface when the high- and low-pressure regions are correctly identified.
Drilling access versus completion access. Protective and permanent components may occupy the same housing at different stages.
Protective and permanent components may occupy the same housing at different stages.
Three interfaces in the handover. These interfaces are close together on a drawing but require different records.
These interfaces are close together on a drawing but require different records.
What “casing hung” establishes. A shift report can confirm the landing event while the packoff test remains outstanding.
A shift report can confirm the landing event while the packoff test remains outstanding.
Mark up the pressure chart. Pairing a chart with its test schematic makes the result interpretable later.
Pairing a chart with its test schematic makes the result interpretable later.

Questions from the field

Is the subsea wellhead the same as the production tree?

The wellhead carries and seals casing. The tree controls well flow and provides access to the completed well. The drawing shows their connection and, for a particular architecture, where the tubing hanger lands.

Does a casing hanger hold pressure by itself?

The hanger body is part of the pressure-containing structure. Annular isolation between the hanger and housing depends on the specified seal assembly and its verified installation.

Why check the external profile if the bore size is already known?

Bore size describes a passage. The external profile determines where the connector engages and how the gasket fits. Two systems described with the same nominal bore can require different connectors.

Historical subsea Christmas tree at the Norwegian Petroleum Museum
The museum tree shows the production equipment mounted above a subsea wellhead after drilling. Photo by Hannes Grobe (CC BY-SA 4.0).

Technical references

Society of Petroleum Engineers, Petroleum Engineering Handbook, Volume II: Drilling Engineering. Chapter 8, §§8.4.1–8.4.6, printed pp. II-358–II-362, especially Figs. 8.21 and 8.24.

Yong Bai and Qiang Bai, Subsea Engineering Handbook. Chapter 22, §22.3, subsea wellhead system and function requirements.

BSEE study of loads at subsea wellhead and riser interfaces.