A workover rig acceptance test asks whether the identified rig, in its installed configuration, can carry out the authorized workover. A rig-wide inspection establishes equipment condition. Acceptance goes one step further by matching that evidence to the well, tubing program and operating envelope. A carrier can hold current certificates and still arrive with the wrong elevator, insufficient tested interface clearance or an unresolved limiting component in the hoisting path.
Define the worst credible job condition before the witness test
Start with the workover program. Record the intended string, expected fluid condition, planned pulling loads and authorized contingency loads. Reconcile whether a stated load is a string load below the elevators, an indicated hookload or a load on an individual component. Use one documented basis, including hook-block and handling-equipment weights where relevant to the manufacturer’s definitions. A single nameplate number is insufficient for a chain of components in series.
Map the actual configuration, including mast and base conditions, reeving, drawworks, brakes, traveling equipment, links and elevators. The current manufacturer and approved engineering documents govern permitted load and setup. A rig’s advertised rating in another reeving or mast configuration cannot release it for this one. If the site requires anchors, guys, leveling or other support, confirm the applicable design and site evidence for the specific unit.

Compare at a common load reference
Suppose the approved planning sheet identifies a required 170,000 lbf at the elevator for a particular contingency and already includes the authorized margins on that basis. The selected elevator is rated 160,000 lbf. The mast package advertises 220,000 lbf in a stated configuration. The planned condition exceeds the elevator rating by 10,000 lbf. The larger number elsewhere in the load path cannot remove this discrepancy.
Record a hold against that operation. The normal anticipated tubing pull might sit below 160,000 lbf, but the planned contingency still cannot be represented as accepted. A replacement must suit the tubular profile as well as the load and satisfy the rest of the hoisting chain. These illustrative values are an arithmetic comparison, not a test load or a required proof-test factor.
The rig acceptance and commissioning guide covers the wider test framework. Compare the proposed demonstration with the workover and drilling rig equipment comparison before signing off a rig-specific function.

Demonstrate interfaces a yard certificate cannot establish
Witness the functions specified in the approved acceptance plan. For tubing handling, verify that the installed elevator or spider matches the tubular, that tongs and backup can reach their authorized grip locations and that the handling sequence clears the pressure-control stack and work platform. A single short pup or oversized accessory can create a different handling case from a standard tubing joint.
For well control, reconcile the current well-specific barrier plan with the installed stack and control equipment. Record equipment IDs, approved pressure and function test documentation and the owner of outstanding actions. A powered movement or successful hydraulic command indicates a function response. It does not establish pressure integrity of every barrier or authorize a change in well status. Pressure and load tests must use the applicable approved procedure and acceptance criteria.


Floor equipment to check at acceptance
| Component | Function | Acceptance and maintenance evidence |
|---|---|---|
| Tubing elevator and links | The elevator engages the tubular. The links carry its load to the hook. | Match the elevator bore and profile to the actual tubing, check the rated load of each item and identify the link set by serial number. Review latch condition, link-eye wear and critical-load inspection records. |
| Spider and slip inserts | The spider holds the string at the floor while the elevators reposition. | Verify the installed slip and insert range against the tubular OD. Record insert condition, retention and function, and the rating for this suspended load. |
| Power tong and backup | The tong applies torque to one joint. The backup reacts it through the lower joint. | Verify grip area and diameter for each tool, the load-cell calibration and the available torque at the selected setting. Look for damaged dies, loose retainers and hydraulic leakage. |
| Mechanical drawworks brake | The handle and linkage apply the bands to the drum. The auxiliary brake assists in controlling descent. | Compare the required lowering duty with the installed configuration. Check linkage pins, retainers, pad and drum wear records and the auxiliary-brake function result. |
Service hours and preventive maintenance evidence
For a service rig with a mechanical band brake, the Canadian Association of Energy Contractors’ RP 10.0, edition 5, §4.1, table 2 gives a concrete example. Brake bands, handle and linkage have Level I checks daily, Level II weekly, Level III annually and Level IV at 24,000 operating hours. The auxiliary brake has Level III at that same 24,000-hour point. Check which row applies. Match the tour sheets and last inspection record to the rig, then reconcile accumulated service-rig hours using the practice’s counting rule. A wear finding can bring replacement forward. The inspection interval does not establish a maximum continuous shift or a guaranteed component life.
The Forum B+V elevator-links manual, rev. 07, §§6.2–6.3 uses a different clock for its links. It specifies daily visual observation, weekly closer inspection, six-monthly Category III inspection and annual Category IV inspection. It also calls for immediate inspection after critical or unexpected loads. At acceptance, establish whether any shock loading or jarring occurred after the last dated inspection and examine its disposition before releasing those links.
Make the scope of release unmistakable
A block-travel limit provides a useful example. Eni’s rig inspection form lists traveling-block limit switches separately from its drawworks and auxiliary-brake checks (pp. 12–13). On a unit fitted with a travel limiter, record the device ID, the trip point and datum specified by the approved rig-specific test, the response expected there, and the response witnessed. An audible warning establishes that the alarm sounded. A claim that the brake or interlock actuated needs its own observed result. A change in reeving or mast configuration calls for review of the affected limits.
Put hook and elevator ratings on a common load basis
If an illustrative static load is 150 klbf below the elevators and the links and elevators together weigh 6 klbf, the corresponding load carried at the hook is 156 klbf before including any other equipment below that reference. Do not add the traveling block’s own weight to that same hook demand; its weight enters a different free-body calculation for the hoisting system.
For each acceptance item name the point of application, which suspended equipment is included, the rig configuration and any dynamic allowance already in the program. Compare the planned load with ratings on the same basis and verify the indicator’s tare convention. A successful function demonstration at a lighter load does not certify an unsupported contingency or set a proof-test load.
What counts as closure of an acceptance exception?
Suppose the only inspected elevators are the 160-klbf set in the example. Record the exact duty withheld, the planned 170-klbf load at those elevators and the equipment identification in the acceptance record. If another set is offered, close the exception against its identity, applicable rating, tubular fit and witnessed interface checks. A generic equipment certificate or a larger hook rating does not close an exception on that elevator set.
Field comparison
| Workover duty | Evidence to request | Example reason to withhold that duty |
|---|---|---|
| Tubing pulling load | Component-level ratings on compatible load bases | Elevator rating below planned elevator load |
| Tubing handling | Actual profiles, tool clearance and witnessed demonstration | Backup cannot reach the specified grip area |
| Pressure control | Well-specific installed configuration and approved test record | Document belongs to a different test boundary |
| Carrier and mast | Site setup and configuration-specific inspection evidence | Support arrangement differs from accepted configuration |

What to record in the field
| Check or record | Job-specific entry |
|---|---|
| Enter the program revision, job envelope and load-reference definitions. | |
| Identify each limiting component and match the installed serial number. | |
| Record observed results, witnesses and the job stage each exception affects. | |
| Retain closure evidence and identify the authority releasing the approved stage. |
Additional technical figures (5)





Questions from the field
Does a rig move invalidate every certificate?
Check each certificate’s scope and the governing requirements. A move can change site and interface conditions even when shop evidence remains valid.
Is a function test equivalent to a proof load or pressure test?
These address different claims and require different procedures. The acceptance record should name exactly what was demonstrated.
Can the service unit start with open punch items?
Only within the documented release scope and approvals. An unresolved item that invalidates a required duty remains a hold on that duty.

Technical references
Workover Operations, chapter 1, Workover Rig and Equipment. PDF pages 10–13, mobile workover rigs and hoisting equipment.
Eni, Land Drilling Rig Inspection Report, STAP-P-1-R-6088. Pages 12–15, rig structure, drawworks and pump inspection evidence.
OSHA, Transporting Rig and Rigging Up. Servicing rig site preparation, rig positioning and setup hazards.
UNIDO reference on drilling rigs and hoisting equipment.